Response text:

October 15, 1975

Mr. I. Ray Coons
President
R. C. Engineering & Construction Company, Inc.
P.O. Box 1695
Pascagoula, Mississippi 39567

Dear Mr. Coons:

This responds to your letter of October 1, 1975, regarding registration with this Department as a qualified corrosion control engineer.

The safety regulations applicable to gas pipelines (49 CFR Part 192) and liquid pipelines (49 CFR Part 195) do not require that corrosion control procedures be conducted by persons registered with this Department.

Sincerely,

Cesar DeLeon
Acting Director
Office of Pipeline
Safety Operations


Regulation Sections

Section Subject
§ 192.453 General